Fact Sheet: Small modular reactors: Still too expensive, too slow and too risky
Summary
The document asserts that small modular reactors are not a viable energy solution due to systemic cost overruns and construction delays, concluding they would arrive too late to replace coal in Australia.
Key insights
- Operational and under-construction SMRs in Russia, China, and Argentina have seen costs increase by three to seven times the original estimates.
- SMR projects in the United States have also experienced significant cost escalations, with estimates doubling or quadrupling since inception.
- Actual construction timelines for SMRs in Russia, China, and Argentina have reached 12-13 years, far exceeding the projected schedules of three to four years.
- In Australia, SMRs would likely not be operational until the 2040s, by which time the Australian Energy Market Operator (AEMO) expects over 90% of generation to be supplied by variable renewables and storage, and coal to have exited the system.
- SMRs are not financially viable as flexible generation because their economics depend on baseload operation; costs per megawatt-hour rise as the capacity factor falls.
Cite the original document
- APA
- Institute for Energy Economics and Financial Analysis (n.d.). Fact Sheet: Small modular reactors: Still too expensive, too slow and too risky. https://ieefa.org/sites/default/files/2024-06/fact-sheet-SMR-AU_1.pdf
- Chicago
- Institute for Energy Economics and Financial Analysis. Fact Sheet: Small modular reactors: Still too expensive, too slow and too risky. n.d. https://ieefa.org/sites/default/files/2024-06/fact-sheet-SMR-AU_1.pdf.
- Wikipedia
- {{cite report |author=Institute for Energy Economics and Financial Analysis |title=Fact Sheet: Small modular reactors: Still too expensive, too slow and too risky |url=https://ieefa.org/sites/default/files/2024-06/fact-sheet-SMR-AU_1.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-001214)}}
- BibTeX
- @techreport{instituteforenergyeconomicsandfinancialanalysisndfact, author = {{Institute for Energy Economics and Financial Analysis}}, title = {{Fact Sheet: Small modular reactors: Still too expensive, too slow and too risky}}, institution = {Institute for Energy Economics and Financial Analysis}, url = {https://ieefa.org/sites/default/files/2024-06/fact-sheet-SMR-AU_1.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-001214} }
Full text
Collected · Record updated