European Pressurized Reactors (EPRs) Next-generation Design Suffers From Old Problems

Report an error

Summary

AI-generated

This summary is written by a language model reading the source document. It is not the publisher's words and is not a substitute for the original.

Learn more about AI enrichment

This report finds that the European Pressurized Reactor (EPR) design is plagued by systemic cost overruns and construction delays, making it an expensive and risky alternative to renewable energy.

Key insights

AI-generated

These insights are written by a language model reading the source document. They are not the publisher's words and are not a substitute for the original.

Learn more about AI enrichment
  • The European Pressurized Reactor (EPR) design has consistently experienced major cost overruns and schedule delays, and these issues have not improved with subsequent projects.
  • In Finland, the Olkiluoto 3 EPR reactor's cost rose from €3 billion to €11 billion, and its expected service date shifted from 2009 to March 2023.
  • France's Flamanville reactor saw costs increase from an original estimate of €3.3 billion to €12.7 billion, with fuel loading not expected before mid-2023.
  • The Hinkley Point C project in the United Kingdom is already one-third over its original budget after less than four years of construction and is delayed by at least two years.
  • Only two EPRs are currently operational, both located in China; however, the Taishan 1 reactor was shut down for over a year due to damaged fuel rods.
  • Nuclear energy construction costs are significantly higher than renewables; the typical overnight cost for a nuclear reactor is USD$6,695/kW, compared to USD$1,718/kW for onshore wind and USD$1,748/kW for solar-plus-storage.

Cite the original document

APA
Bass, F. (2023). European Pressurized Reactors (EPRs) Next-generation Design Suffers From Old Problems. Institute for Energy Economics and Financial Analysis. https://ieefa.org/sites/default/files/2023-02/European%20Pressurized%20Reactors_February%202023.pdf
Chicago
Bass, Frank. European Pressurized Reactors (EPRs) Next-generation Design Suffers From Old Problems. Institute for Energy Economics and Financial Analysis, 2023. https://ieefa.org/sites/default/files/2023-02/European%20Pressurized%20Reactors_February%202023.pdf.
Wikipedia
{{cite report |last1=Bass |first1=Frank |title=European Pressurized Reactors (EPRs) Next-generation Design Suffers From Old Problems |publisher=Institute for Energy Economics and Financial Analysis |date=February 2023 |url=https://ieefa.org/sites/default/files/2023-02/European%20Pressurized%20Reactors_February%202023.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-001172)}}
BibTeX
@techreport{bass2023european, author = {Bass, Frank}, title = {{European Pressurized Reactors (EPRs) Next-generation Design Suffers From Old Problems}}, institution = {Institute for Energy Economics and Financial Analysis}, year = {2023}, month = feb, url = {https://ieefa.org/sites/default/files/2023-02/European%20Pressurized%20Reactors_February%202023.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-001172} }

Full text

Collected · Record updated