Long-Term Power Plant Contracts Saddle AMP Communities With High Electricity Prices

Report an error

Summary

AI-generated

This summary is written by a language model reading the source document. It is not the publisher's words and is not a substitute for the original.

Learn more about AI enrichment

This report finds that AMP member communities are paying significantly higher electricity prices than projected due to massive cost overruns and underperformance of the Prairie State coal plant and the Combined Hydro Project.

Key insights

AI-generated

These insights are written by a language model reading the source document. They are not the publisher's words and are not a substitute for the original.

Learn more about AI enrichment
  • The actual cost of power from the Prairie State coal-fired plant and the Combined Hydro Project has significantly exceeded the projections presented by American Municipal Power (AMP) in 2007, occurring while wholesale market prices in the PJM region were declining.
  • For the Prairie State plant, IEEFA estimates the average cost charged to Cleveland Public Power (CPP) between 2012 and 2019 was $67.50 per MWh, which is 40% higher than AMP's projections and 90% higher than PJM market costs.
  • The Combined Hydro Project has been even more expensive, with member communities paying an average of $178.60 per MWh since 2016, representing a 167% increase over projected costs and a 269% increase over PJM market costs.
  • Cleveland Public Power is estimated to have paid at least $106 million more for power from these two projects between 2012 and 2019 than it would have if it had purchased capacity and energy from the wholesale PJM markets.
  • Three primary factors drove the higher-than-projected costs: construction cost overruns, lower-than-expected power production, and significant completion delays.
  • Construction costs for the 1600MW Prairie State plant increased by $1 billion (approximately 20%) over the original $4 billion estimate, while the Combined Hydro Project's cost rose from an estimated $4,360 per kW in 2007 to over $10,800 per kW.
  • Operational underperformance occurred at both sites; Prairie State produced an average of 9.6 million MWh annually between 2012 and 2019, falling short of the 11.8 million MWh projected by AMP.
  • The Combined Hydro Project experienced severe delays, with the Cannelton, Willow Island, and Smithland plants coming online in 2016 and 2017, despite anticipated commercial operation dates in 2013 and 2014.

Cite the original document

APA
Schlissel, D. (2020). Long-Term Power Plant Contracts Saddle AMP Communities With High Electricity Prices. Institute for Energy Economics and Financial Analysis. https://ieefa.org/sites/default/files/resources/AMP-Communities-Saddled-With-High-Electricity-Prices_September-2020.pdf
Chicago
Schlissel, David. Long-Term Power Plant Contracts Saddle AMP Communities With High Electricity Prices. Institute for Energy Economics and Financial Analysis, 2020. https://ieefa.org/sites/default/files/resources/AMP-Communities-Saddled-With-High-Electricity-Prices_September-2020.pdf.
Wikipedia
{{cite report |last1=Schlissel |first1=David |title=Long-Term Power Plant Contracts Saddle AMP Communities With High Electricity Prices |publisher=Institute for Energy Economics and Financial Analysis |date=September 2020 |url=https://ieefa.org/sites/default/files/resources/AMP-Communities-Saddled-With-High-Electricity-Prices_September-2020.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-000936)}}
BibTeX
@techreport{schlissel2020longterm, author = {Schlissel, David}, title = {{Long-Term Power Plant Contracts Saddle AMP Communities With High Electricity Prices}}, institution = {Institute for Energy Economics and Financial Analysis}, year = {2020}, month = sep, url = {https://ieefa.org/sites/default/files/resources/AMP-Communities-Saddled-With-High-Electricity-Prices_September-2020.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-000936} }

Full text

Collected · Record updated