IEEFA Argentina: Government cannot afford subsidies for Vaca Muerta oil and gas producers
Summary
This briefing concludes that Argentina's plans for Vaca Muerta are ill-conceived because the government cannot afford the necessary infrastructure investments or the production subsidies required to attract foreign investment.
Key insights
- The Argentine government has retroactively cut production subsidies and stopped approving new projects, leading to a potential lawsuit from Techint (parent of Tecpetrol) over US$ 1.45 billion in owed subsidies for 2018.
- Critical pipeline infrastructure is missing to meet export goals, which include increasing oil exports from 30,000 to 490,000 barrels per day by 2023; a project to connect Vaca Muerta to Buenos Aires and its export seaport is estimated at $1.2 to $2 billion but lacks a financing plan.
- The government's strategy to use Public Private Partnerships (PPPs) for infrastructure is failing due to country risk and falling bond prices, resulting in the suspension of US$21 billion in planned investments between 2019 and 2023.
- Total public infrastructure investments in the energy, transportation, and logistics sectors are expected to reach US$ 30 billion over the next four years, a cost the document describes as cost-prohibitive for the Argentine economy.
Cite the original document
- APA
- Sanzillo, K. H. T. (2019). IEEFA Argentina: Government cannot afford subsidies for Vaca Muerta oil and gas producers. Institute for Energy Economics and Financial Analysis. https://ieefa.org/resources/ieefa-update-financing-lags-critical-infrastructure-meet-vaca-muerta-patagonia-fracking
- Chicago
- Sanzillo, Kathy Hipple Tom. IEEFA Argentina: Government cannot afford subsidies for Vaca Muerta oil and gas producers. Institute for Energy Economics and Financial Analysis, 2019. https://ieefa.org/resources/ieefa-update-financing-lags-critical-infrastructure-meet-vaca-muerta-patagonia-fracking.
- Wikipedia
- {{cite report |last1=Sanzillo |first1=Kathy Hipple Tom |title=IEEFA Argentina: Government cannot afford subsidies for Vaca Muerta oil and gas producers |publisher=Institute for Energy Economics and Financial Analysis |date=5 April 2019 |url=https://ieefa.org/resources/ieefa-update-financing-lags-critical-infrastructure-meet-vaca-muerta-patagonia-fracking |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-000802)}}
- BibTeX
- @techreport{sanzillo2019ieefa, author = {Sanzillo, Kathy Hipple Tom}, title = {{IEEFA Argentina: Government cannot afford subsidies for Vaca Muerta oil and gas producers}}, institution = {Institute for Energy Economics and Financial Analysis}, year = {2019}, month = apr, url = {https://ieefa.org/resources/ieefa-update-financing-lags-critical-infrastructure-meet-vaca-muerta-patagonia-fracking}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-000802} }
Full text
Collected · Record updated