Do headline cost estimates for projects like Ksi Lisims understate stakeholder risks?
Summary
The Ksi Lisims LNG project's estimated costs have risen from an initial CAD$8-9 billion to as high as CAD$30 billion, illustrating a recurring pattern of cost overruns in major Canadian fossil fuel infrastructure.
Key insights
- The initial cost estimates for the Ksi Lisims LNG project, which ranged from CAD$8 billion to $9 billion, appear to have been an underestimate when compared to industry benchmarks for floating LNG plants, which range from CAD$1,500-$2,450 per MTPA of LNG.
- Recent public announcements indicate the budget for the Ksi Lisims facility has increased to CAD$30 billion, which is more than triple the original estimate of CAD$8.3 billion to $9 billion.
- Ksi Lisims is part of a broader trend in Canada where major fossil fuel projects, including Woodfibre LNG, the Coastal Gas Link pipeline, and the Trans Mountain expansion project, have repeatedly experienced substantial cost overruns.
- Underestimating capital costs creates risks for the public when government subsidies or tax incentives are involved, as public resources are diverted from lower-cost investments aligned with climate objectives.
Cite the original document
- APA
- Kalegha, M. (2026). Do headline cost estimates for projects like Ksi Lisims understate stakeholder risks? Institute for Energy Economics and Financial Analysis. https://ieefa.org/resources/do-headline-cost-estimates-projects-ksi-lisims-understate-stakeholder-risks
- Chicago
- Kalegha, Mark. Do headline cost estimates for projects like Ksi Lisims understate stakeholder risks? Institute for Energy Economics and Financial Analysis, 2026. https://ieefa.org/resources/do-headline-cost-estimates-projects-ksi-lisims-understate-stakeholder-risks.
- Wikipedia
- {{cite press release |last1=Kalegha |first1=Mark |title=Do headline cost estimates for projects like Ksi Lisims understate stakeholder risks? |publisher=Institute for Energy Economics and Financial Analysis |date=13 October 2026 |url=https://ieefa.org/resources/do-headline-cost-estimates-projects-ksi-lisims-understate-stakeholder-risks |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-000318)}}
- BibTeX
- @misc{kalegha2026headline, author = {Kalegha, Mark}, title = {{Do headline cost estimates for projects like Ksi Lisims understate stakeholder risks?}}, publisher = {Institute for Energy Economics and Financial Analysis}, year = {2026}, month = oct, url = {https://ieefa.org/resources/do-headline-cost-estimates-projects-ksi-lisims-understate-stakeholder-risks}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-000318} }
Full text
Collected · Record updated