Economics behind Indonesia’s dimethyl ether (DME) push are hard to justify

Report an error

Summary

AI-generated

This summary is written by a language model reading the source document. It is not the publisher's words and is not a substitute for the original.

Learn more about AI enrichment

The report concludes that Indonesia's push for dimethyl ether (DME) is financially unfeasible, as production costs would result in energy prices 42% higher than imported LPG.

Key insights

AI-generated

These insights are written by a language model reading the source document. They are not the publisher's words and are not a substitute for the original.

Learn more about AI enrichment
  • A proposed 1.4 million tonne DME plant in Sumatra is estimated to cost USD 2.6 billion in capital expenditure and USD 520 million in lost opportunity costs over ten years, totaling USD 3.1 billion.
  • DME production costs are estimated between USD 614 and USD 651 per tonne, making it 42% more expensive per unit of energy than the March 2025 LPG price of USD 615 per metric tonne (adjusted for energy content).
  • The economic risk of DME production is highlighted by the case of China's Shanxi Lanhua, which halted its DME production in 2023 due to unprofitability, losing USD 73 per tonne in 2022 and 2023.
  • While a 1.4 million tonne DME plant could offset 15% of Indonesia's LPG imports, the investment is deemed unfeasible because producing each tonne of DME would still incur a loss of USD 66, representing a negative profit margin of 12%.

Cite the original document

APA
Peh, G. (2025). Economics behind Indonesia’s dimethyl ether (DME) push are hard to justify. Institute for Energy Economics and Financial Analysis. https://ieefa.org/resources/economics-behind-indonesias-dimethyl-ether-dme-push-are-hard-justify
Chicago
Peh, Ghee. Economics behind Indonesia’s dimethyl ether (DME) push are hard to justify. Institute for Energy Economics and Financial Analysis, 2025. https://ieefa.org/resources/economics-behind-indonesias-dimethyl-ether-dme-push-are-hard-justify.
Wikipedia
{{cite report |last1=Peh |first1=Ghee |title=Economics behind Indonesia’s dimethyl ether (DME) push are hard to justify |publisher=Institute for Energy Economics and Financial Analysis |date=27 March 2025 |url=https://ieefa.org/resources/economics-behind-indonesias-dimethyl-ether-dme-push-are-hard-justify |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-000172)}}
BibTeX
@techreport{peh2025economics, author = {Peh, Ghee}, title = {{Economics behind Indonesia’s dimethyl ether (DME) push are hard to justify}}, institution = {Institute for Energy Economics and Financial Analysis}, year = {2025}, month = mar, url = {https://ieefa.org/resources/economics-behind-indonesias-dimethyl-ether-dme-push-are-hard-justify}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-000172} }

Full text

Collected · Record updated