Five ways to save the Capacity Investment Scheme from "zombie projects"
Summary
The author argues that Australia's Capacity Investment Scheme risks funding 'zombie projects' that never reach construction and proposes reforms such as oversubscribing tender rounds and requiring prior planning approvals to ensure the 2030 renewable energy targets are met.
Key insights
- To meet the 82% renewable energy target by 2030, Australia may need 32GW of new large-scale renewable energy projects for the National Electricity Market (NEM) and South West Interconnected System (SWIS) grids, requiring 8GW of new projects per annum from 2024 to 2027.
- The Capacity Investment Scheme (CIS) risks creating 'zombie projects'—projects that win tenders at low prices but lack realistic prospects of advancing—which can take two to three years to be identified as failures.
- The author proposes that the CIS should oversubscribe tender rounds, making underwriting contracts contingent on projects being committed to construction before a specific capacity target is met, to maintain competitive pressure on developers.
- A standing offer underwriting contract should be established for projects that reach construction commitment regardless of the proponent's credentials, specifically to encourage smaller projects (below 200MW) that can bypass transmission constraints.
- Tender eligibility should be restricted to projects that already possess necessary government planning and environmental approvals to avoid delays; in New South Wales, wind project planning approvals have averaged nearly 10 years.
- The CIS should maintain tenders on a national basis rather than pre-allocating capacity to individual states via 'Renewable Energy Transformation Agreements' to foster competition and ensure better value for taxpayers.
- Criteria regarding community engagement and social licence should be removed from the tender process and handled through planning approval policies to avoid vague qualitative criteria and political interference.
Cite the original document
- APA
- Edis, T. (2024). Five ways to save the Capacity Investment Scheme from "zombie projects". Institute for Energy Economics and Financial Analysis. https://ieefa.org/resources/five-ways-save-capacity-investment-scheme-attack-zombies
- Chicago
- Edis, Tristan. Five ways to save the Capacity Investment Scheme from "zombie projects". Institute for Energy Economics and Financial Analysis, 2024. https://ieefa.org/resources/five-ways-save-capacity-investment-scheme-attack-zombies.
- Wikipedia
- {{cite report |last1=Edis |first1=Tristan |title=Five ways to save the Capacity Investment Scheme from "zombie projects" |publisher=Institute for Energy Economics and Financial Analysis |date=9 May 2024 |url=https://ieefa.org/resources/five-ways-save-capacity-investment-scheme-attack-zombies |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-000116)}}
- BibTeX
- @techreport{edis2024five, author = {Edis, Tristan}, title = {{Five ways to save the Capacity Investment Scheme from "zombie projects"}}, institution = {Institute for Energy Economics and Financial Analysis}, year = {2024}, month = may, url = {https://ieefa.org/resources/five-ways-save-capacity-investment-scheme-attack-zombies}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-000116} }
Full text
Collected · Record updated