The document asserts that Kosovo's obstacles to renewable energy are political, noting that a Swiss-funded feasibility study contradicted World Bank claims regarding wind energy viability.
Key insights
- Proponents of the New Kosovo Power plant misrepresent a 2011 World Bank Options study to claim limited wind and solar capacity, whereas the study actually indicated 1000 MW of wind power is possible, albeit using a conservative 25% capacity factor.
- A feasibility study for the Zatric Wind Farm, conducted under the Swiss government, refuted World Bank claims that wind energy was not viable due to wind speeds, terrain, and grid issues, finding that wind speeds could support a 35-40MW farm and terrain issues were manageable.
- Despite government plans from 2013 to increase wind and solar contributions by 2015, 2015 annual generation statistics from the Energy Regulatory Office show that Kosovo consumed no energy from these resources in 2015.
- There are currently five pending wind projects (179 MW) and nine pending solar projects (15 MW) facing bureaucratic delays and mixed government signals caused by the push for a new coal plant.
- A World Bank investment of $31.9 million for energy efficiency in public buildings has been rated as 'moderately unsatisfactory' and is at 'substantial risk' due to procurement problems.
Cite the original document
- APA
- Sanzillo, T., & Azemi, V. (2016). Obstacles to building renewable power in Kosovo are political, not technical. Institute for Energy Economics and Financial Analysis. https://ieefa.org/resources/obstacles-building-renewable-power-kosovo-are-political-not-technical
- Chicago
- Sanzillo, Tom, and Visar Azemi. Obstacles to building renewable power in Kosovo are political, not technical. Institute for Energy Economics and Financial Analysis, 2016. https://ieefa.org/resources/obstacles-building-renewable-power-kosovo-are-political-not-technical.
- Wikipedia
- {{cite press release |last1=Sanzillo |first1=Tom |last2=Azemi |first2=Visar |title=Obstacles to building renewable power in Kosovo are political, not technical |publisher=Institute for Energy Economics and Financial Analysis |date=20 May 2016 |url=https://ieefa.org/resources/obstacles-building-renewable-power-kosovo-are-political-not-technical |access-date=5 November 2026 |via=Climate Insights Directory (document ieefa-000023)}}
- BibTeX
- @misc{sanzillo2016obstacles, author = {Sanzillo, Tom and Azemi, Visar}, title = {{Obstacles to building renewable power in Kosovo are political, not technical}}, publisher = {Institute for Energy Economics and Financial Analysis}, year = {2016}, month = may, url = {https://ieefa.org/resources/obstacles-building-renewable-power-kosovo-are-political-not-technical}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document ieefa-000023} }
Full text
Collected · Record updated