Energiewende und bürgerbeteiligung: Öffentliche Akzeptanz von Infrastruktur-Projekten am Beispiel der „Thüringer Strombrücke“

Report an error

Summary

AI-generated

This summary is written by a language model reading the source document. It is not the publisher's words and is not a substitute for the original.

Learn more about AI enrichment

This report evaluates the 380-kV grid expansion in Thuringia, finding that while local route optimization was successful, the overall public acceptance remained low because the fundamental necessity of the project was legally predetermined and not subject to open discourse.

Key insights

AI-generated

These insights are written by a language model reading the source document. They are not the publisher's words and are not a substitute for the original.

Learn more about AI enrichment
  • The legal framework of the Energieleitungsausbaugesetz (EnLAG) effectively blocked a discursive exchange of arguments regarding the necessity of the 380-kV grid expansion by legally predetermining its energy-economic necessity.
  • Public acceptance for the project was significantly hindered by a lack of transparency and a perceived 'information gap,' as the grid operator (50Hertz) was often seen as the sole source of data and was accused of an insufficient information policy.
  • Formal participation processes, such as the Raumordnungsverfahren (ROV) and Planfeststellungsverfahren (PFV), were found to be effective for the local optimization of the route but failed to increase the fundamental acceptance of the project.
  • Informal processes, driven by citizen initiatives and local municipalities, were crucial for introducing alternative technologies, such as high-temperature cables and temperature monitoring, which were eventually recognized at the federal level.
  • The activation of the public in formal processes relied heavily on official gazettes (Amtsblätter), which were rarely read by citizens, meaning that broad participation was instead achieved through the private engagement of sensitized individuals and citizen initiatives.
  • The report recommends that for future projects, the necessity of specific lines should not be legally fixed in advance but should be justified and debated within the Planfeststellungsverfahren (PFV) to foster acceptance.
  • The study suggests establishing a separate 'framework process' (Rahmenprozess) to better link informal participation with formal legal procedures, ensuring early information and a higher level of discourse.

Cite the original document

APA
Schnelle, K., & Voigt, M. (2012). Energiewende und bürgerbeteiligung: Öffentliche Akzeptanz von Infrastruktur-Projekten am Beispiel der „Thüringer Strombrücke“. Germanwatch. https://www.germanwatch.org/sites/default/files/publication/4135.pdf
Chicago
Schnelle, Kerstin, and Matthias Voigt. Energiewende und bürgerbeteiligung: Öffentliche Akzeptanz von Infrastruktur-Projekten am Beispiel der „Thüringer Strombrücke“. Germanwatch, 2012. https://www.germanwatch.org/sites/default/files/publication/4135.pdf.
Wikipedia
{{cite report |last1=Schnelle |first1=Kerstin |last2=Voigt |first2=Matthias |title=Energiewende und bürgerbeteiligung: Öffentliche Akzeptanz von Infrastruktur-Projekten am Beispiel der „Thüringer Strombrücke“ |publisher=Germanwatch |date=April 2012 |url=https://www.germanwatch.org/sites/default/files/publication/4135.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document gerwat-001185)}}
BibTeX
@techreport{schnelle2012energiewende, author = {Schnelle, Kerstin and Voigt, Matthias}, title = {{Energiewende und bürgerbeteiligung: Öffentliche Akzeptanz von Infrastruktur-Projekten am Beispiel der „Thüringer Strombrücke“}}, institution = {Germanwatch}, year = {2012}, month = apr, url = {https://www.germanwatch.org/sites/default/files/publication/4135.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document gerwat-001185} }

Full text

Collected · Record updated