Review of Waste-to-Energy National Strategic Project in Indonesia

Report an error

Summary

AI-generated

This summary is written by a language model reading the source document. It is not the publisher's words and is not a substitute for the original.

Learn more about AI enrichment

This report concludes that Indonesia's Waste-to-Energy (WtE) National Strategic Projects are fundamentally flawed, citing high default risks, public health hazards, and a mismatch between incineration technology and the high organic content of Indonesian waste.

Key insights

AI-generated

These insights are written by a language model reading the source document. They are not the publisher's words and are not a substitute for the original.

Learn more about AI enrichment
  • Waste-to-Energy (WtE) incineration is poorly suited for Indonesia because the waste composition is dominated by organic materials and paper, which are not ideal feedstocks for energy generation and may require additional energy to process.
  • Implementing WtE can increase regional government waste management budgets by 2 to 3 times compared to landfill models, while potentially increasing the carbon footprint by 70% relative to landfill systems.
  • The WtE Sunter project in Jakarta failed to achieve financial close due to deadlocks between stakeholders over Power Purchase Agreements (PPA) and tipping fee commitments, as well as the financial instability of Jakarta Propertindo Ltd. (Jakpro).
  • The WtE Putri Cempo facility in Surakarta has caused significant environmental and health issues, including the discharge of untreated wastewater into the Jengglong and Bengawan Solo Rivers and the release of fly ash causing respiratory problems for local residents.
  • The WtE Putri Cempo project's financial model is deemed unfeasible, with an estimated EBITDA that could range from IDR 354 billion to a loss of IDR 617 billion over 20 years, partly because actual energy generation is significantly lower than the 10 MW projection.
  • The WtE Benowo facility in Surabaya is associated with a lack of transparency, with the government rejecting requests for Environmental Impact Assessment (EIA) documents on the grounds of copyright, and reports of increased Acute Respiratory Infections (ARI) in children nearby.
  • The financial structure of WtE Gedebage is high-risk, with a Debt-to-Equity Ratio (DER) of 2.57, which is twice the industry average, and a projected financial performance (Z-score) consistently below the minimum recommendation, indicating a high risk of bankruptcy.
  • WtE projects in Indonesia often conflict with the waste management hierarchy by requiring a stable, high-volume feedstock of waste, which discourages waste reduction and recycling efforts.

Cite the original document

APA
Global Alliance for Incinerator Alternatives (n.d.). Review of Waste-to-Energy National Strategic Project in Indonesia. https://www.no-burn.org/wp-content/uploads/2025/05/EN-SOWING-THE-SEEDS-OF-DESTRUCTION_052025.pdf
Chicago
Global Alliance for Incinerator Alternatives. Review of Waste-to-Energy National Strategic Project in Indonesia. n.d. https://www.no-burn.org/wp-content/uploads/2025/05/EN-SOWING-THE-SEEDS-OF-DESTRUCTION_052025.pdf.
Wikipedia
{{cite report |author=Global Alliance for Incinerator Alternatives |title=Review of Waste-to-Energy National Strategic Project in Indonesia |url=https://www.no-burn.org/wp-content/uploads/2025/05/EN-SOWING-THE-SEEDS-OF-DESTRUCTION_052025.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document gaia-000347)}}
BibTeX
@techreport{globalallianceforincineratoralternativesndreview, author = {{Global Alliance for Incinerator Alternatives}}, title = {{Review of Waste-to-Energy National Strategic Project in Indonesia}}, institution = {Global Alliance for Incinerator Alternatives}, url = {https://www.no-burn.org/wp-content/uploads/2025/05/EN-SOWING-THE-SEEDS-OF-DESTRUCTION_052025.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document gaia-000347} }