Manual Operativo para la Adquisición e Instalación de Equipos de Eficiencia Energética en Edificios Públicos de Costa Rica
Summary
The document outlines a comprehensive framework for public institutions in Costa Rica to implement energy efficiency upgrades. It details a lifecycle process including energy diagnostics (Level 1 and 2), the establishment of an evaluation committee, the definition of technological solutions, and a structured procurement process. The guide is grounded in three demonstrative projects: refrigeration upgrades at the Programa Integral de Mercadeo Agropecuario (PIMA), and lighting and climatization improvements at the Hospital Nacional Geriátrico Dr. Raúl Blanco Cervantes. It provides specific technical specifications for LED lighting, inverter air conditioning, and ammonia screw compressors, while offering templates for bidding documents (carteles), contracts, and evaluation matrices. Key emphasis is placed on Life Cycle Costing (LCC) rather than initial cost, and the implementation of Monitoring, Reporting, and Verification (MRV) to validate energy savings.
Key insights
- The guide establishes a two-level energy audit system to identify opportunities: Level 1 is a basic diagnostic based on at least 12 months of billing analysis, while Level 2 involves a detailed analysis of energy use and consumption to establish an energy balance and conduct technical and financial analyses.
- Project prioritization is based on five weighted criteria: Replicability and scalability (30%), Project visibility (15%), Energy saving potential and economic viability (20%), Significant investment (20%), and Social and economic benefits (15%). Projects must achieve a total score of 75% or higher to be selectable.
- The procurement process emphasizes Life Cycle Costing (LCC) over initial CAPEX, requiring contractors to provide a detailed analysis of acquisition, installation, operation, maintenance, and end-of-life waste disposal costs.
- Three demonstrative projects were implemented: a refrigeration system upgrade at the Programa Integral de Mercadeo Agropecuario (PIMA) involving a 250 HP screw compressor, and lighting and climatization upgrades at the Hospital Nacional Geriátrico Dr. Raúl Blanco Cervantes.
- Technical specifications for lighting upgrades at the hospital required the replacement of fluorescent tubes with T8 LED tubes (17-20 W for 48" tubes) with a minimum luminous flux of 2,100 lm and a minimum lifespan of 50,000 hours.
- Climatization specifications for the hospital focused on Inverter technology with a SEER of 16 or higher and the use of refrigerants with a Global Warming Potential (GWP) of less than 750, such as R32 or R290.
- The refrigeration project at PIMA involved replacing a 40-year-old compressor with a high-efficiency 250 HP screw compressor using anhydrous ammonia (NH3) as the refrigerant, with a target investment of up to 280,000 USD.
- The guide identifies a significant financial barrier for public sector energy efficiency in Costa Rica: the inability to acquire medium-term debt and the administrative complexity of managing financing with sovereign guarantees, which prevents the creation of revolving funds.
- A structured payment model is proposed for contractors: a 50% advance payment upon contract signing and guarantee delivery, 40% upon installation and delivery of specific milestones, and a final 10% after the verification of committed energy efficiency.
Cite the original document
- APA
- Guzmán, G., Rivera, F., & Magallón, D. (n.d.). Manual Operativo para la Adquisición e Instalación de Equipos de Eficiencia Energética en Edificios Públicos de Costa Rica. Basel Agency for Sustainable Energy. https://energy-base.org/wp-content/uploads/2025/02/Manual-Reporte-EE-En-Edificios-Publicos-CR.pdf
- Chicago
- Guzmán, Gabriela, Fernando Rivera, and Daniel Magallón. Manual Operativo para la Adquisición e Instalación de Equipos de Eficiencia Energética en Edificios Públicos de Costa Rica. Basel Agency for Sustainable Energy, n.d. https://energy-base.org/wp-content/uploads/2025/02/Manual-Reporte-EE-En-Edificios-Publicos-CR.pdf.
- Wikipedia
- {{cite report |last1=Guzmán |first1=Gabriela |last2=Rivera |first2=Fernando |last3=Magallón |first3=Daniel |title=Manual Operativo para la Adquisición e Instalación de Equipos de Eficiencia Energética en Edificios Públicos de Costa Rica |publisher=Basel Agency for Sustainable Energy |url=https://energy-base.org/wp-content/uploads/2025/02/Manual-Reporte-EE-En-Edificios-Publicos-CR.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document enbase-000066)}}
- BibTeX
- @techreport{guzmnndmanual, author = {Guzmán, Gabriela and Rivera, Fernando and Magallón, Daniel}, title = {{Manual Operativo para la Adquisición e Instalación de Equipos de Eficiencia Energética en Edificios Públicos de Costa Rica}}, institution = {Basel Agency for Sustainable Energy}, url = {https://energy-base.org/wp-content/uploads/2025/02/Manual-Reporte-EE-En-Edificios-Publicos-CR.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document enbase-000066} }