Combating corruption and improving procurement practices in South Africa
Summary
The report argues that South Africa's multi-trillion Rand energy infrastructure programme is highly susceptible to corruption and poor planning, recommending the adoption of sustainable public procurement and increased civil society oversight to protect public funds.
Key insights
- The South African state's Strategic Infrastructure Projects (SIPs) involve a massive allocation for energy infrastructure, totaling R2.3 trillion or 67.6% of the R3.2 trillion envisaged by National Treasury.
- The procurement of a nuclear fleet, projected at R300 billion, is identified as the biggest state tender in South Africa's history and carries significant risks of corruption and financial burden.
- The Integrated Resource Plan 2010 (IRP2010) is criticized for lacking prudent planning, as it was finalized before the Integrated Energy Plan and the National Development Plan, and it fails to apply 'learning curves' to nuclear and coal technologies.
- There is a pervasive problem of 'tenderpreneurs' in South Africa, where individuals use personal and political connections to enrich themselves through corrupt government tender awards.
- The Department of Energy's New Generation Regulations have increased ministerial discretion and reduced the oversight capacity of the National Treasury, particularly regarding the determination of new generation capacity needs.
- The Pebble Bed Modular Reactor (PBMR) project is cited as a failure in public procurement, absorbing R8.67 billion of taxpayers' money over 11 years before being shut down in 2010 due to technical difficulties and lack of investors.
- The report recommends the adoption of Sustainable Public Procurement (SPP) and whole-life costing to integrate environmental, social, and economic considerations and prevent risky investments.
- The draft Infrastructure Development Bill is criticized for potentially violating constitutional rights to a healthy environment by fast-tracking projects and disregarding established environmental impact assessment (EIA) procedures.
- The Renewable Energy Independent Power Producer Procurement Process (RE IPPPP) is noted for its use of competitive bidding, though it is criticized by some for high compliance burdens and a lack of public consultation compared to the earlier REFIT model.
- The report advocates for the use of public procurement portals, similar to those in Slovakia, and the implementation of Integrity Pacts to increase transparency and curb corruption.
Cite the original document
- APA
- Earthlife Africa (2013). Combating corruption and improving procurement practices in South Africa. https://earthlife.org.za/wp-content/uploads/2020/06/Dodgy-Energy-Deals_ELA-Report_130509_web.pdf
- Chicago
- Earthlife Africa. Combating corruption and improving procurement practices in South Africa. 2013. https://earthlife.org.za/wp-content/uploads/2020/06/Dodgy-Energy-Deals_ELA-Report_130509_web.pdf.
- Wikipedia
- {{cite report |author=Earthlife Africa |title=Combating corruption and improving procurement practices in South Africa |date=May 2013 |url=https://earthlife.org.za/wp-content/uploads/2020/06/Dodgy-Energy-Deals_ELA-Report_130509_web.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document earthli-000024)}}
- BibTeX
- @techreport{earthlifeafrica2013combating, author = {{Earthlife Africa}}, title = {{Combating corruption and improving procurement practices in South Africa}}, institution = {Earthlife Africa}, year = {2013}, month = may, url = {https://earthlife.org.za/wp-content/uploads/2020/06/Dodgy-Energy-Deals_ELA-Report_130509_web.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document earthli-000024} }
Full text
Collected · Record updated