The report finds that while Scotland's peak electricity demand was highly secure in early 2017, the closure of nuclear stations by 2030 will likely necessitate new transmission links or schedulable generation capacity to maintain security-of-supply.

Key insights

AI-generated

These insights are written by a language model reading the source document. They are not the publisher's words and are not a substitute for the original.

Learn more about AI enrichment
  • In the winter of 2016/17, the combination of the Scottish generation fleet and a secure import capability of 2.65GW provided over 99.9% confidence in meeting peak demand, provided sufficient generation was available in the rest of Great Britain.
  • To maintain a 99% confidence level in meeting a peak demand of up to 6.2 GW by 2030 (approximately 15% higher than 2016), secure import requirements are estimated to be between 2.9GW and 3.7GW, assuming Peterhead power station remains operational.
  • The closure of Peterhead power station would increase the required secure import capability by between 350MW and 400MW.
  • The 2017 commissioning of the western HVDC link between Hunterston and Deeside is expected to increase secure import capability by approximately 1.2GW, though imports of 3.5GW or more may require further network reinforcements or increased coordination across Great Britain.
  • Wind generation reduces the need for secure imports; the 2016 wind fleet of 5.5GW offset the need for 700MW of secure import capability, representing a regional capacity credit of 12%.
  • Interconnection with Norway and Northern Ireland can reduce the required imports from the rest of Great Britain, but the reduction is less than the total installed capacity. For example, 1.85GW of interconnector capacity only reduces the secure import requirement by approximately 1.0GW at a 99% confidence level.
  • Beyond peak demand, other security-of-supply issues include the need for voltage control, system stability provided by large synchronous generators, and 'black start' capabilities for recovering from a total system blackout.

Cite the original document

APA
Gill, S., & Bell, K. (2017). Meeting Scotland’s peak demand for electricity. ClimateXChange. https://www.climatexchange.org.uk/wp-content/uploads/2023/09/cxc_security_of_electricity_supply_short_report.pdf
Chicago
Gill, Simon, and Keith Bell. Meeting Scotland’s peak demand for electricity. ClimateXChange, 2017. https://www.climatexchange.org.uk/wp-content/uploads/2023/09/cxc_security_of_electricity_supply_short_report.pdf.
Wikipedia
{{cite report |last1=Gill |first1=Simon |last2=Bell |first2=Keith |title=Meeting Scotland’s peak demand for electricity |publisher=ClimateXChange |date=March 2017 |url=https://www.climatexchange.org.uk/wp-content/uploads/2023/09/cxc_security_of_electricity_supply_short_report.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document climex-000408)}}
BibTeX
@techreport{gill2017meeting, author = {Gill, Simon and Bell, Keith}, title = {{Meeting Scotland’s peak demand for electricity}}, institution = {ClimateXChange}, year = {2017}, month = mar, url = {https://www.climatexchange.org.uk/wp-content/uploads/2023/09/cxc_security_of_electricity_supply_short_report.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document climex-000408} }

Full text

Collected · Record updated