Network investment costs of the domesc heat and transport transion in Scotland
Summary
The report finds that reinforcing Scotland's distribution networks for heat pumps and electric vehicles would cost between £1.10bn and £2.48bn in discounted capex, with flexibility solutions potentially reducing these costs by one-third.
Key insights
- Maximum annual recovery costs per household for the full investment timeline until 2050 range from £7.20 to £23.35 in a high-demand, low-flexibility scenario, falling to between £3.75 and £11.81 in a lower-cost scenario incorporating network flexibility.
- For the 2023-2028 charging period, modelled annual recovery costs per household range from £0.82 to £6.07, depending on the region, technology uptake, and use of flexibility solutions.
- Network investment recovery costs are primarily based on unit consumption, meaning properties with higher electricity usage will contribute a larger proportion toward reinforcement costs.
- The 'System Transformation' (ST) scenario's investment profile is the most comparable to the published RIIO-ED2 business plans of the distribution network operators (DNOs).
Cite the original document
- APA
- G., J. N. M., Yates, M., Morris, O., Hanna, B., & Pedro, N. F. (2023). Network investment costs of the domesc heat and transport transion in Scotland. ClimateXChange. https://www.climatexchange.org.uk/wp-content/uploads/2023/12/CXC-Network-investment-costs-of-the-domestic-heat-and-transport-transition-in-Scotland-Oct-2023.pdf
- Chicago
- G., J. Nicholas Melchor, Mat Yates, Owen Morris, Beth Hanna, and Nuno Fernandes Pedro. Network investment costs of the domesc heat and transport transion in Scotland. ClimateXChange, 2023. https://www.climatexchange.org.uk/wp-content/uploads/2023/12/CXC-Network-investment-costs-of-the-domestic-heat-and-transport-transition-in-Scotland-Oct-2023.pdf.
- Wikipedia
- {{cite report |last1=G. |first1=J. Nicholas Melchor |last2=Yates |first2=Mat |last3=Morris |first3=Owen |last4=Hanna |first4=Beth |last5=Pedro |first5=Nuno Fernandes |title=Network investment costs of the domesc heat and transport transion in Scotland |publisher=ClimateXChange |date=June 2023 |url=https://www.climatexchange.org.uk/wp-content/uploads/2023/12/CXC-Network-investment-costs-of-the-domestic-heat-and-transport-transition-in-Scotland-Oct-2023.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document climex-000322)}}
- BibTeX
- @techreport{g2023network, author = {G., J. Nicholas Melchor and Yates, Mat and Morris, Owen and Hanna, Beth and Pedro, Nuno Fernandes}, title = {{Network investment costs of the domesc heat and transport transion in Scotland}}, institution = {ClimateXChange}, year = {2023}, month = jun, url = {https://www.climatexchange.org.uk/wp-content/uploads/2023/12/CXC-Network-investment-costs-of-the-domestic-heat-and-transport-transition-in-Scotland-Oct-2023.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document climex-000322} }
Full text
Collected · Record updated