The report finds that deploying 2.5 GW of rooftop solar in Scotland by 2030 could overload 27% of primary substations, requiring an estimated £150 million in distribution network and over £150 million in transmission network reinforcements.

Key insights

AI-generated

These insights are written by a language model reading the source document. They are not the publisher's words and are not a substitute for the original.

Learn more about AI enrichment
  • The solar industry has proposed an ambition of 4-6 GW of solar photovoltaic (PV) capacity by 2030 to align Scotland with the UK target of 70 GW by 2035, consisting of 1.5 GW domestic rooftop, 1 GW commercial rooftop, and the remainder as large-scale ground-mounted solar.
  • Current Distribution Network Operator (DNO) forecasts significantly underestimate solar uptake; the highest projected scenario ('Leading the Way') forecasts only approximately 325 MW, which is 13% of the 2.5 GW industry ambition.
  • An additional 2.5 GW of rooftop solar could cause 209 primary substations (27% of the total) in Scotland to become overloaded. The impact is concentrated in the Scottish Power Energy Networks (SPEN) region, where 46% of primary substations may require intervention, compared to 9% in the Scottish & Southern Electricity Networks (SSEN) region.
  • High-level estimates for distribution network reinforcement costs to accommodate 2.5 GW of rooftop solar are £130 million for SPEN (upgrading high-voltage substations and low-voltage networks) and £20 million for SSEN, with additional transmission infrastructure costs of £120 million for SPEN and £30 million for SSEN.
  • The socialisation of distribution reinforcement costs is estimated to increase annual domestic energy bills by £1.81 in the SPEN area and £0.53 in the SSEN area. Non-domestic bills would increase by £24.46 in the SPEN area and £7.17 in the SSEN area.
  • Transmission network reinforcement costs in Scotland are estimated to exceed £150 million, with 81% (£122 million) occurring in the SPEN transmission network and 19% (£30 million) in the SSEN transmission network.
  • Voltage rises are the primary concern for DNOs, particularly in summer when excess generation flows in reverse onto the network, potentially damaging infrastructure and appliances.
  • Co-locating battery storage with solar PV is identified as a key mitigation strategy to reduce network impacts by absorbing excess solar and preventing exports, thereby delaying or reducing the need for expensive network upgrades.
  • Innovative network management tools, such as flexible connection agreements, network reconfiguration using remote controlled switches, and low-voltage monitoring, can release capacity and reduce traditional reinforcement needs, though they cannot entirely negate them.

Cite the original document

APA
Kelly, M., Sharma, M., & Solanki, L. (2023). Impacts of high-volume solar deployment. ClimateXChange. https://www.climatexchange.org.uk/wp-content/uploads/2024/11/CXC-Impact-of-high-volume-solar-PV-deployment-November-2024.pdf
Chicago
Kelly, Michael, Mohit Sharma, and Lalit Solanki. Impacts of high-volume solar deployment. ClimateXChange, 2023. https://www.climatexchange.org.uk/wp-content/uploads/2024/11/CXC-Impact-of-high-volume-solar-PV-deployment-November-2024.pdf.
Wikipedia
{{cite report |last1=Kelly |first1=Michael |last2=Sharma |first2=Mohit |last3=Solanki |first3=Lalit |title=Impacts of high-volume solar deployment |publisher=ClimateXChange |date=December 2023 |url=https://www.climatexchange.org.uk/wp-content/uploads/2024/11/CXC-Impact-of-high-volume-solar-PV-deployment-November-2024.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document climex-000297)}}
BibTeX
@techreport{kelly2023impacts, author = {Kelly, Michael and Sharma, Mohit and Solanki, Lalit}, title = {{Impacts of high-volume solar deployment}}, institution = {ClimateXChange}, year = {2023}, month = dec, url = {https://www.climatexchange.org.uk/wp-content/uploads/2024/11/CXC-Impact-of-high-volume-solar-PV-deployment-November-2024.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document climex-000297} }

Full text

Collected · Record updated