A letter from the National Energy Regulator of South Africa (NERSA) to the Centre for Environmental Rights (CER) regarding the status of the Thabametsi and Khanyisa IPP power station projects.
Key insights
- NERSA has decided not to finalize the Thabametsi application due to the existence of a court judgement.
- The processing of the Khanyisa application is contingent upon the applicant obtaining the Integrated Water Use Licence (IWUL). NERSA states it will not halt applications based on pending court cases unless a court decision renders proceeding impossible, provided all prerequisites are met.
Cite the original document
- APA
- Centre for Environmental Rights (n.d.). letter_cer_thabametsi-and-khanyisa-8d137fd1833bb6a6.pdf. https://cer.org.za/wp-content/uploads/2018/03/Letter_CER_Thabametsi-and-Khanyisa.pdf?x21779
- Chicago
- Centre for Environmental Rights. letter_cer_thabametsi-and-khanyisa-8d137fd1833bb6a6.pdf. n.d. https://cer.org.za/wp-content/uploads/2018/03/Letter_CER_Thabametsi-and-Khanyisa.pdf?x21779.
- Wikipedia
- {{cite press release |author=Centre for Environmental Rights |title=letter_cer_thabametsi-and-khanyisa-8d137fd1833bb6a6.pdf |url=https://cer.org.za/wp-content/uploads/2018/03/Letter_CER_Thabametsi-and-Khanyisa.pdf?x21779 |access-date=17 August 2026 |via=Climate Insights Directory}}
- BibTeX
- @misc{centreforenvironmentalrightsndlettercerthabametsiandkhanyisa8d137fd1833bb6a6pdf, author = {{Centre for Environmental Rights}}, title = {{letter\_cer\_thabametsi-and-khanyisa-8d137fd1833bb6a6.pdf}}, publisher = {Centre for Environmental Rights}, url = {https://cer.org.za/wp-content/uploads/2018/03/Letter_CER_Thabametsi-and-Khanyisa.pdf?x21779}, urldate = {2026-08-17}, note = {Indexed by Climate Insights Directory} }
Full text
Collected · Record updated