A letter from Kriel Power Station to the Nkangaia District Municipality detailing emission limit exceedances for the 2015/16 financial year and the specific technical and operational remediation measures taken to address NEMA Section 30 incidents.
Key insights
- Kriel Power Station submitted a letter on 23 August 2016 to the Nkangaia District Municipality to explain instances where emission limits were exceeded during the 2015/16 financial year and to outline remediation measures to prevent recurrence. This submission supplemented an Annual Emission Report dated 25 May 2016, which was delivered on 31 May 2016, in accordance with Section 18 d) of the Minimum Emission Standards.
- The document lists several NEMA Section 30 incidents from the 2015/16 financial year and their corresponding remediation actions. These include technical repairs such as replacing the SO3 blower skid and SO3 motor, repairing a leaking pipe on the Unit 6 blow tank, and repairing mechanical damage in the Unit 6 ESP caused by hopper levels. Other measures involved operational changes, such as compiling a risk assessment for operating units with SO3 panel doors open for cooling and improving plant monitoring.
Cite the original document
- APA
- Centre for Environmental Rights (n.d.). kriel-power-station-annual-emission-reporting-requirements-3768a696c2417372.pdf. https://cer.org.za/wp-content/uploads/2017/07/Kriel-Power-Station-Annual-Emission-Reporting-Requirements.pdf?x21779
- Chicago
- Centre for Environmental Rights. kriel-power-station-annual-emission-reporting-requirements-3768a696c2417372.pdf. n.d. https://cer.org.za/wp-content/uploads/2017/07/Kriel-Power-Station-Annual-Emission-Reporting-Requirements.pdf?x21779.
- Wikipedia
- {{cite press release |author=Centre for Environmental Rights |title=kriel-power-station-annual-emission-reporting-requirements-3768a696c2417372.pdf |url=https://cer.org.za/wp-content/uploads/2017/07/Kriel-Power-Station-Annual-Emission-Reporting-Requirements.pdf?x21779 |access-date=17 August 2026 |via=Climate Insights Directory}}
- BibTeX
- @misc{centreforenvironmentalrightsndkrielpowerstationannualemissionreportingrequirements3768a696c2417372pdf, author = {{Centre for Environmental Rights}}, title = {{kriel-power-station-annual-emission-reporting-requirements-3768a696c2417372.pdf}}, publisher = {Centre for Environmental Rights}, url = {https://cer.org.za/wp-content/uploads/2017/07/Kriel-Power-Station-Annual-Emission-Reporting-Requirements.pdf?x21779}, urldate = {2026-08-17}, note = {Indexed by Climate Insights Directory} }
Full text
Collected · Record updated