The report tracks 48 federal capital projects across Akwa Ibom, Cross River, Delta, and Rivers states, revealing significant issues with project abandonment, substandard quality, and potential corruption. While many projects were completed, the authors identify a pattern of underfunding, poor oversight, and lack of transparency, particularly in empowerment schemes and legislator-facilitated contracts.
Key insights
- Across the four tracked states, a total of 11.073 billion Naira was analyzed, with 10.240 billion Naira marked as completed, 159.1 million Naira as ongoing, 574.4 million Naira as not done, and 101.76 million Naira as underdelivered.
- In Akwa Ibom, 15 projects worth 481.3 million Naira were tracked; eight were completed (273.2 million Naira), one was ongoing (52.4 million Naira), five were not done (142.7 million Naira), and one could not be located (12.9 million Naira).
- In Cross River, 8 projects worth 7.4 billion Naira were tracked, with five completed (7.1 billion Naira), two undone (329.5 million Naira), and one paid for but not located (59.8 million Naira).
- In Delta, 9 projects worth 1.04 billion Naira were tracked; three were completed (947.6 million Naira), one was ongoing (16.1 million Naira), two were 'fraudulently delivered' (28.9 million Naira), and three were not completed (46.9 million Naira).
- In Rivers, 16 projects worth 2.1 billion Naira were tracked, with ten completed (1.96 billion Naira), two ongoing (90.6 million Naira), and four not done (53 million Naira).
- The report identifies systemic failures including substandard infrastructure, such as potholes in a recently completed 6.5 billion Naira road project in Ugep and a 1.1 billion Naira road rehabilitation project in Rivers.
- Evidence suggests potential conflicts of interest and lack of transparency in procurement, specifically citing a solar streetlight project in Cross Rivers executed by a company affiliated with the project facilitator, Senator Agom Jarigbe.
- The report notes that underfunding is a major cause of abandoned projects, citing examples in Rivers where funds for drainage and flood control were deemed 'grossly inadequate'.
Cite the original document
- APA
- Opaluwa, E., Osiyemi, J., Awotoye, K., James, A., Eze, M., Otei, J., & Odagwe, C. (2025). Project Tracking Report on Public Service Delivery in Oil-Producing Communities. BudgIT. https://budgit.org/wp-content/uploads/2025/11/Project-Tracking-Report-Oxfam.pdf
- Chicago
- Opaluwa, Enebi, Joshua Osiyemi, Kofoworola Awotoye, Akpan James, Mercy Eze, Joshua Otei, and Chukwunwike Odagwe. Project Tracking Report on Public Service Delivery in Oil-Producing Communities. BudgIT, 2025. https://budgit.org/wp-content/uploads/2025/11/Project-Tracking-Report-Oxfam.pdf.
- Wikipedia
- {{cite report |last1=Opaluwa |first1=Enebi |last2=Osiyemi |first2=Joshua |last3=Awotoye |first3=Kofoworola |last4=James |first4=Akpan |last5=Eze |first5=Mercy |last6=Otei |first6=Joshua |last7=Odagwe |first7=Chukwunwike |title=Project Tracking Report on Public Service Delivery in Oil-Producing Communities |publisher=BudgIT |date=2025 |url=https://budgit.org/wp-content/uploads/2025/11/Project-Tracking-Report-Oxfam.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document budgit-000215)}}
- BibTeX
- @techreport{opaluwa2025project, author = {Opaluwa, Enebi and Osiyemi, Joshua and Awotoye, Kofoworola and James, Akpan and Eze, Mercy and Otei, Joshua and Odagwe, Chukwunwike}, title = {{Project Tracking Report on Public Service Delivery in Oil-Producing Communities}}, institution = {BudgIT}, year = {2025}, url = {https://budgit.org/wp-content/uploads/2025/11/Project-Tracking-Report-Oxfam.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document budgit-000215} }
Full text
Collected · Record updated