A coalition of civil society organizations argues that Uganda's 2020 ESIA regulations grant excessive discretionary power to NEMA, which risks environmental and human rights violations. The group recommends mandatory public hearings and extended consultation periods to ensure effective public participation.
Key insights
- The 2020 regulations grant NEMA discretionary power to decide whether to consult lead agencies or the public on terms of reference (ToR) for ESIA studies, which may undermine the scrutiny needed to protect community livelihoods and the environment.
- Current consultation timeframes are insufficient: the minimum seven-day notice for stakeholder consultations is too short for effective preparation, and NEMA's ability to specify a 'lesser period' for lead agency comments undermines their capacity to review long ESIA reports.
- Regulation 20(1) restricts the review of ESIA studies to local project areas, excluding the general public despite the fact that sectors like oil and gas have climate change impacts affecting the wider Ugandan public and the global population.
- NEMA has discretionary power over whether to hold public hearings and how to invite comments via mass media, which the authors claim can be abused; they cite the 2020 failure to organize public hearings for Hoima Sugar Ltd’s Kyangwali Mixed Land Use project in Bugoma forest as an example.
- The authors recommend several specific reforms, including increasing the minimum notice for community consultations to 14 days, ensuring a minimum of 21 days for the public to submit views on ESIA reports, and making public hearings mandatory for controversial projects with significant or transboundary impacts.
Cite the original document
- APA
- Africa Institute for Energy Governance (n.d.). final-letter-to-mwe-to-review-2020-esia-regulations-06-may-2022-dd000d3b424076c6.pdf. https://www.afiego.org/wp-content/uploads/2024/03/Final-letter-to-MWE-to-review-2020-ESIA-regulations-06-May-2022.pdf
- Chicago
- Africa Institute for Energy Governance. final-letter-to-mwe-to-review-2020-esia-regulations-06-may-2022-dd000d3b424076c6.pdf. n.d. https://www.afiego.org/wp-content/uploads/2024/03/Final-letter-to-MWE-to-review-2020-ESIA-regulations-06-May-2022.pdf.
- Wikipedia
- {{cite press release |author=Africa Institute for Energy Governance |title=final-letter-to-mwe-to-review-2020-esia-regulations-06-may-2022-dd000d3b424076c6.pdf |url=https://www.afiego.org/wp-content/uploads/2024/03/Final-letter-to-MWE-to-review-2020-ESIA-regulations-06-May-2022.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document afiego-000066)}}
- BibTeX
- @misc{africainstituteforenergygovernancendfinallettertomwetoreview2020esiaregulations06may2022dd000d3b424076c6pdf, author = {{Africa Institute for Energy Governance}}, title = {{final-letter-to-mwe-to-review-2020-esia-regulations-06-may-2022-dd000d3b424076c6.pdf}}, publisher = {Africa Institute for Energy Governance}, url = {https://www.afiego.org/wp-content/uploads/2024/03/Final-letter-to-MWE-to-review-2020-ESIA-regulations-06-May-2022.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document afiego-000066} }
Full text
Collected · Record updated