PRESS STATEMENT: CAUTIONARY NOTE TO THE MINISTRY OF ENERGY ON THE AMERI POWER PLANT

Report an error

Summary

AI-generated

This summary is written by a language model reading the source document. It is not the publisher's words and is not a substitute for the original.

Learn more about AI enrichment

The Africa Centre for Energy Policy (ACEP) warns that the relocation and maintenance of the the AMERI power plant to Kumasi is overpriced and unnecessary, as the Volta River Authority (VRA) has the capacity to operate it and upgrading transmission lines is a more cost-effective solution for power stability.

Key insights

AI-generated

These insights are written by a language model reading the source document. They are not the publisher's words and are not a substitute for the original.

Learn more about AI enrichment
  • The Ministry of Energy relieved AMERI Energy of its contractual obligations to perform rectification works on four of the plant's 10 units before the transfer of title, despite an independent assessment by WSP recommending such works.
  • The cost of relocating the AMERI plant from Takoradi to Kumasi and its subsequent three-year maintenance is estimated at $71.6 million, with the relocation cost alone increasing by 40% from an initial proposal of $25.48 million to $35.6 million.
  • The Volta River Authority (VRA) possesses the technical capacity to operate and maintain the plant, making the sole-sourced O&M contract with Mytilineos SA unnecessary and an additional cost burden.
  • Upgrading the National Interconnected Transmission System (NITS), specifically the Western Corridor Transmission Lines and the 330KV Pokuase-Anwomaso Transmission Line, is a cheaper and quicker fix for power instability in the middle belt than relocating plants.
  • The Ministry of Energy's use of sole-sourcing for the EPC and O&M contracts to Mytilineos SA is questioned, as long service is not a valid justification for sole-sourcing under the PPA Act.
  • Ghana's power sector faces severe financial distress, with under-recoveries of GHS 14 billion in 2020 and 2021, and outstanding payments for gas and IPPs exceeding $1.2 billion in the first half of 2022.

Cite the original document

APA
Africa Centre for Energy Policy (2022). PRESS STATEMENT: CAUTIONARY NOTE TO THE MINISTRY OF ENERGY ON THE AMERI POWER PLANT. https://acep.africa/wp-content/uploads/2023/03/PRESS-STATEMENT-CAUTIONARY-NOTE-TO-THE-MINISTRY-OF-ENERGY-ON-THE-AMERI-POWER-PLANT-.pdf
Chicago
Africa Centre for Energy Policy. PRESS STATEMENT: CAUTIONARY NOTE TO THE MINISTRY OF ENERGY ON THE AMERI POWER PLANT. 2022. https://acep.africa/wp-content/uploads/2023/03/PRESS-STATEMENT-CAUTIONARY-NOTE-TO-THE-MINISTRY-OF-ENERGY-ON-THE-AMERI-POWER-PLANT-.pdf.
Wikipedia
{{cite press release |author=Africa Centre for Energy Policy |title=PRESS STATEMENT: CAUTIONARY NOTE TO THE MINISTRY OF ENERGY ON THE AMERI POWER PLANT |date=2 August 2022 |url=https://acep.africa/wp-content/uploads/2023/03/PRESS-STATEMENT-CAUTIONARY-NOTE-TO-THE-MINISTRY-OF-ENERGY-ON-THE-AMERI-POWER-PLANT-.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document acep-000150)}}
BibTeX
@misc{africacentreforenergypolicy2022press, author = {{Africa Centre for Energy Policy}}, title = {{PRESS STATEMENT: CAUTIONARY NOTE TO THE MINISTRY OF ENERGY ON THE AMERI POWER PLANT}}, publisher = {Africa Centre for Energy Policy}, year = {2022}, month = aug, url = {https://acep.africa/wp-content/uploads/2023/03/PRESS-STATEMENT-CAUTIONARY-NOTE-TO-THE-MINISTRY-OF-ENERGY-ON-THE-AMERI-POWER-PLANT-.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document acep-000150} }

Full text

Collected · Record updated