This report analyzes the failure of the ECG concession, finding that the agreement was terminated in October 2019 primarily due to the provision of fraudulent insurance guarantees and a lack of financial capacity among local partners.

Key insights

AI-generated

These insights are written by a language model reading the source document. They are not the publisher's words and are not a substitute for the original.

Learn more about AI enrichment
  • The requirement for 51 percent local content was implemented without a robust plan to raise the minimum investment of $250 million, contributing to an uncompetitive bidding process as stronger companies withdrew.
  • MERALCO, as the technical and financial lead, failed to select capable Ghanaian partners who could contribute their required share of the investment.
  • The Millennium Development Authority (MiDA) failed to conduct required due diligence on the local partners of the PDS consortium to assess their capabilities and net worth, which was required to be at least $400 million.
  • The Ghanaian Parliament failed to perform due diligence on the consortium's structure, allowing political debates over local content to overshadow concerns about the financial capacity of local companies.
  • MiDA marginalized the Electricity Company of Ghana (ECG) during the process, assuming ECG's role in negotiations and facilitating the change from bank guarantees to insurance guarantees despite ECG's objections.
  • Transaction advisors failed to detect the risk of PDS's inability to invest in the sector and instead proposed steps to convert bank guarantees into insurance guarantees when PDS could not provide the former.
  • The concession was terminated on October 18, 2019, after investigations revealed that the insurance guarantees provided by Al Koot were fraudulent, as the company was not authorized to underwrite such risk and signatures were forged.
  • An FTI Consulting forensic audit confirmed that PDS's inability to raise bank guarantees was due to the consortium lacking the required capital for the transaction.

Cite the original document

APA
Africa Centre for Energy Policy (n.d.). d4f305fb-an-assessment-of-the-implementation-challenges-of-the-power-contract-0f95b0fd9cbb952c.pdf. https://acep.africa/wp-content/uploads/2023/03/d4f305fb-an-assessment-of-the-implementation-challenges-of-the-power-contract.pdf
Chicago
Africa Centre for Energy Policy. d4f305fb-an-assessment-of-the-implementation-challenges-of-the-power-contract-0f95b0fd9cbb952c.pdf. n.d. https://acep.africa/wp-content/uploads/2023/03/d4f305fb-an-assessment-of-the-implementation-challenges-of-the-power-contract.pdf.
Wikipedia
{{cite report |author=Africa Centre for Energy Policy |title=d4f305fb-an-assessment-of-the-implementation-challenges-of-the-power-contract-0f95b0fd9cbb952c.pdf |url=https://acep.africa/wp-content/uploads/2023/03/d4f305fb-an-assessment-of-the-implementation-challenges-of-the-power-contract.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document acep-000102)}}
BibTeX
@techreport{africacentreforenergypolicyndd4f305fbanassessmentoftheimplementationchallengesofthepowercontract0f95b0fd9cbb952cpdf, author = {{Africa Centre for Energy Policy}}, title = {{d4f305fb-an-assessment-of-the-implementation-challenges-of-the-power-contract-0f95b0fd9cbb952c.pdf}}, institution = {Africa Centre for Energy Policy}, url = {https://acep.africa/wp-content/uploads/2023/03/d4f305fb-an-assessment-of-the-implementation-challenges-of-the-power-contract.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document acep-000102} }

Full text

Collected · Record updated