ACEP’S COMMENTS ON THE AMERI RENEGOTIATED CONTRACT
Summary
The Africa Centre for Energy Policy (ACEP) concludes that the renegotiated AMERI contract is more burdensome than the original, potentially increasing the total cost for the 250MW plant from $510 million to $1.375 billion over approximately 18 years.
Key insights
- The proposed amendment to the AMERI contract is more expensive than the original deal, with a total cash flow for the renegotiated deal reaching $1,125,007,380. When combined with payments already made for the executed portion of the original contract, the total cost to the government for the 250MW plant is estimated at $1.375 billion over approximately 18 years, compared to the original $510 million.
- Under the proposed novation, Mytilineos International Trading Company Ltd assumes $300 million of government's outstanding liability in exchange for a 15-year deal. Mytilineos will be paid $75 million annually, totaling $1.125 billion over the period, resulting in projected gains of $825 million for the company.
- ACEP argues that the government's claim of $405.06 million in savings is inaccurate and misleading because it is based on a general tariff reduction rather than focusing on the capacity charges component. ACEP's analysis suggests that while capacity charges would decrease by 1.8201 cents/kWh for the remaining 2.5 years of the original contract (saving $89.69 million), the government will incur a cost of $937.5 million over the subsequent 12.5 years under the new amendment.
- The renegotiation fails to remove the $150 million profit AMERI was expected to make as a middleman, as Mytilineos has agreed to settle AMERI's interest. Furthermore, METKA, the EPC contractor owned by the same person as Mytilineos, sees its entitlement prolonged by 13 years, moving from a 5-year deal at $72 million to a 15-year deal at $75 million per year.
Cite the original document
- APA
- Africa Centre for Energy Policy (2018). ACEP’S COMMENTS ON THE AMERI RENEGOTIATED CONTRACT. https://acep.africa/wp-content/uploads/2023/03/AMERIRENEGOTIATEDCONTRACT.pdf
- Chicago
- Africa Centre for Energy Policy. ACEP’S COMMENTS ON THE AMERI RENEGOTIATED CONTRACT. 2018. https://acep.africa/wp-content/uploads/2023/03/AMERIRENEGOTIATEDCONTRACT.pdf.
- Wikipedia
- {{cite press release |author=Africa Centre for Energy Policy |title=ACEP’S COMMENTS ON THE AMERI RENEGOTIATED CONTRACT |date=27 July 2018 |url=https://acep.africa/wp-content/uploads/2023/03/AMERIRENEGOTIATEDCONTRACT.pdf |access-date=5 November 2026 |via=Climate Insights Directory (document acep-000078)}}
- BibTeX
- @misc{africacentreforenergypolicy2018aceps, author = {{Africa Centre for Energy Policy}}, title = {{ACEP’S COMMENTS ON THE AMERI RENEGOTIATED CONTRACT}}, publisher = {Africa Centre for Energy Policy}, year = {2018}, month = jul, url = {https://acep.africa/wp-content/uploads/2023/03/AMERIRENEGOTIATEDCONTRACT.pdf}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document acep-000078} }
Full text
Collected · Record updated