ACEP's response to the statement by the Ministry of Power on the Ameri Energy Power Project
Summary
The Africa Centre for Energy Policy (ACEP) contends that the Ameri Energy Power Project's BOOT structure is effectively a high-cost procurement of turbines, potentially costing US$510 million for a US$220 million project.
Key insights
- ACEP argues that while the Ameri deal is a Build, Own, Operate and Transfer (BOOT) agreement rather than an outright purchase, the cumulative payments over five years effectively constitute the cost of procuring the turbines. The organization questions the value for money of a project where a US$220 million investment could result in payments of US$510 million, excluding operation and maintenance costs, given that the benchmark cost of capital (Libor) is less than 1%.
- Contrary to claims by the Ministry of Power that no payments for equipment will be made, ACEP asserts that monthly payments by the Volta River Authority (VRA) constitute payment for the turbines. These payments include US$850,000 per turbine per month for ten turbines (US$8.5 million monthly or US$102 million annually), plus US$16.6 million in variable costs, totaling nearly US$120 million due to Ameri and its partners.
Cite the original document
- APA
- ACEP (2015). ACEP's response to the statement by the Ministry of Power on the Ameri Energy Power Project. Africa Centre for Energy Policy. https://acep.africa/aceps-response-to-the-statement-by-the-ministry-of-power-on-the-ameri-energy-power-project/
- Chicago
- ACEP. ACEP's response to the statement by the Ministry of Power on the Ameri Energy Power Project. Africa Centre for Energy Policy, 2015. https://acep.africa/aceps-response-to-the-statement-by-the-ministry-of-power-on-the-ameri-energy-power-project/.
- Wikipedia
- {{cite press release |last1=ACEP |title=ACEP's response to the statement by the Ministry of Power on the Ameri Energy Power Project |publisher=Africa Centre for Energy Policy |date=22 December 2015 |url=https://acep.africa/aceps-response-to-the-statement-by-the-ministry-of-power-on-the-ameri-energy-power-project/ |access-date=5 November 2026 |via=Climate Insights Directory (document acep-000005)}}
- BibTeX
- @misc{acep2015aceps, author = {ACEP}, title = {{ACEP's response to the statement by the Ministry of Power on the Ameri Energy Power Project}}, publisher = {Africa Centre for Energy Policy}, year = {2015}, month = dec, url = {https://acep.africa/aceps-response-to-the-statement-by-the-ministry-of-power-on-the-ameri-energy-power-project/}, urldate = {2026-11-05}, note = {Indexed by Climate Insights Directory, document acep-000005} }
Full text
Collected · Record updated